Uttarakhand tunnel collapse: Rescuers drill new tunnels for trapped workers, pipe installed to supply food
Silkyara/IBNS: As the 41 labourers remain trapped inside an under-construction tunnel in Uttarakhand following a wall collapse for more than a week, the agencies involved in the rescue operation are working on an alternative plan which involves tunnelling sideways and boring from the top to build a vertical shaft.
The Centre has come up with a five-option action plan that involves drilling from three sides to access the trapped workers. Five different agencies have been tasked with carrying out each operation.
Two tunnels will be drilled horizontally from the right and left sides of the main tunnel, while a vertical shaft will be drilled from the top of the tunnel.
The labourers have been trapped in a 400-metre buffer zone of the unfinished main tunnel since November 12 when a portion of the 4.5-km tunnel on the Brahmakhal-Yamunotri National Highway collapsed, trapping 41 workers.
The tunnel -- meant to join Silkyara and Dandalgaon in Uttarkashi -- is part of the Char Dham project.
However, the big challenge is finding space for the multiple drilling machines needed in the hilly terrain and the time-consuming job of building motorable roads, which has already started.
At present, a single machine is operating in the area, clearing the way for a heavier machine. Workers are building a ramp from the main tunnel's entrance to its roof to transport the heavier machines.
On Monday morning, a wider pipe was brought and is currently being installed. This will allow rescuers to deliver a wider variety of food and medicine to the trapped people.
Earlier, only dry fruits could be sent in. With the new pipe, the authorities will be able to provide more substantial meals.
An international tunnelling expert team arrived at the spot and the International Tunnelling and Underground Space Association president Arnold Dix is overseeing the operations.
A robotics team from defence research organization DRDO has also reached.
Over the last week, several plans to cut through the 40-meter rock wall fell through.
The last rock fall took place on Friday when attempts were made to use an American Auger drill flown in from Delhi. The drill machine that was being used before that had broken down and work had to be stopped till the new one reached.
Top Headlines
-
News
Israel: Benjamin Netanyahu's office admits staff did not pass information ahead of Hamas attack
March 02, 2025
-
News
Trump-Zelenskyy fiery exchange triggers pro-Ukraine protests across USA
March 02, 2025
-
News
'Make a deal or we are out': Donald Trump tells Volodymyr Zelenskyy at White House
February 28, 2025
-
News
BJP to announce JP Nadda's successor as party chief soon: Reports
February 27, 2025
-
News
There is no IIT in Ranchi: Centre rejects Congress leader Sam Pitroda's hacking claim
February 27, 2025
-
News
India's technological sector expected to touch USD 300-350 billion in five years, says Rajnath Singh
February 25, 2025
-
News
Magnitude 5.1 earthquake strikes Bay of Bengal, tremors felt in Kolkata
February 24, 2025
-
News
Washington Post says Trumps claim of $21 million US funding for Indias voter turnout false
February 23, 2025
-
News
PM Modi shares idea to promote 'science' in Mann Ki Baat address
February 23, 2025
-
News
FIR against Farah Khan for 'derogatory' remark on Holi festival
February 21, 2025