Uttarakhand tunnel collapse: Rescuers drill new tunnels for trapped workers, pipe installed to supply food
Silkyara/IBNS: As the 41 labourers remain trapped inside an under-construction tunnel in Uttarakhand following a wall collapse for more than a week, the agencies involved in the rescue operation are working on an alternative plan which involves tunnelling sideways and boring from the top to build a vertical shaft.
The Centre has come up with a five-option action plan that involves drilling from three sides to access the trapped workers. Five different agencies have been tasked with carrying out each operation.
Two tunnels will be drilled horizontally from the right and left sides of the main tunnel, while a vertical shaft will be drilled from the top of the tunnel.
The labourers have been trapped in a 400-metre buffer zone of the unfinished main tunnel since November 12 when a portion of the 4.5-km tunnel on the Brahmakhal-Yamunotri National Highway collapsed, trapping 41 workers.
The tunnel -- meant to join Silkyara and Dandalgaon in Uttarkashi -- is part of the Char Dham project.
However, the big challenge is finding space for the multiple drilling machines needed in the hilly terrain and the time-consuming job of building motorable roads, which has already started.
At present, a single machine is operating in the area, clearing the way for a heavier machine. Workers are building a ramp from the main tunnel's entrance to its roof to transport the heavier machines.
On Monday morning, a wider pipe was brought and is currently being installed. This will allow rescuers to deliver a wider variety of food and medicine to the trapped people.
Earlier, only dry fruits could be sent in. With the new pipe, the authorities will be able to provide more substantial meals.
An international tunnelling expert team arrived at the spot and the International Tunnelling and Underground Space Association president Arnold Dix is overseeing the operations.
A robotics team from defence research organization DRDO has also reached.
Over the last week, several plans to cut through the 40-meter rock wall fell through.
The last rock fall took place on Friday when attempts were made to use an American Auger drill flown in from Delhi. The drill machine that was being used before that had broken down and work had to be stopped till the new one reached.
Top Headlines
-
News
In a setback for Donald Trump, US judge orders federal agencies to rehire fired workers: Report
March 13, 2025
-
News
Tamil Nadu govt's move to replace rupee symbol signals a dangerous mindset: Nirmala Sitharaman
March 13, 2025
-
News
'Nothing more than a temporary breather for Ukraine': Vladimir Putin aide slams ceasefire proposal
March 13, 2025
-
News
Ranya Rao shares how she received consignment at Dubai airport, learnt how to conceal gold bars on YouTube
March 13, 2025
-
News
'People are going to Russia right now as we speak: Donald Trump on Ukraine war ceasefire talks
March 12, 2025
-
News
Pakistani army claims to have freed all hostages in passenger train siege; 28 personnel killed
March 12, 2025
-
News
Europe holds high-level talks on rearming continent, boosting Ukraine aid
March 12, 2025
-
News
180 passengers, mostly soldiers, held hostage as Baloch Liberation Army hijack train in Pakistan
March 12, 2025
-
News
Ukraine agrees to proposal for a 30-day general ceasefire with Russia, US to resume military aid
March 11, 2025
-
News
Mark Carney set to succeed Justin Trudeau as Canada PM
March 10, 2025